NBL HISTORY

Timeline of the NBL
Evolution of water training

WIF-->WETF-->NBS-->NBL

    Reduced part–task training

    Increased integrated training

    Increased training quality

    Better timeline fidelity

    Improvement in facility loading

    (training time vs. reconfiguration time)

Apr 1995:   NBL"ground" breaking (modifications to existing facility)

Dec 1995:   Tank construction complete water supply/filtration construction

May 1996:   Tank fill complete (28 days)

Oct 1996:   Systems certification complete integrated suited testing begins

Dec 1996:   ORI Certification for single side operations; NASA assumes ownership

Jun 1997:   ORI Certification for dual (5 suit) operations

Oct 1998:   MOD accepts responsibility for NBL from Space and Life Sciences as DX Division formed

Jan 2002:   Training EMU processing and EVA tool processing moved to NBL from offsite facility (USA)

Mar 2002:   MOD accepts responsibility for LMF from Engineering Directorate


Sonny Carter Training Facility - Neutral Buoyancy Laboratory
Johnson Space Center
Houston, Texas
(281) 792-5999
NASA - National Aeronautics and Space Administration Responsible NASA official: Ronald Lee
Curator:  NBL Webmaster
NASA JSC Web Policies
NASA JSC Home Page
NASA Home Page
Last Updated: April 4, 2007